Avendren® uses proprietary manufacturing and construction processes to give you high-quality, permanent buildings for learning environments that are durable, well-ventilated, accessible, and affordable. Learn more about our process and see just how quickly and easily you can have a new classroom, office, or other space ready to serve your learning community.
All Avendren® buildings come pre-approved. Learn More
Our permanent factory-built structures have been approved by the Division of the State Architect (DSA) for 15 climate zones and with the latest earthquake ratings, making the construction process easier and faster wherever your school is located. Quality construction, flexible infrastructure, and on-demand expansion you can count on for decades.
Complete accessibility for all learners and educators. Learn More
Avendren™ is committed to making learning accessible to all, not only by providing high-quality budget-conscious construction options but by ensuring that all buildings are ADA friendly. We're committed to making the classroom a safe and easy destination for all.
Off-site construction for cleaner, safer projects. Learn More
Avendren™ uses a controlled construction environment to provide expert execution on every project, with fewer materials and personnel needed on site, less interference/interruption on your campus, and fewer variables that affect time, quality, and project outcomes.
High value and fixed costs for a budget-friendly building. Learn More
Factory-made permanent structures give you durable and lasting structures, without the risk of cost overruns or construction delays. Whether you need a single classroom or a full school, we have you covered, typically within 60 days from site readiness.
Everything your school needs, nothing you don't want. Learn More
Reverse-engineered to meet the needs of 21st century learners and communities, Avendren™ buildings are an affordable way to add more classrooms and other needed facilities without excess waste, added expenses, and high long-term maintenance demands.
Our Process
Step 1
Starting Your Avendren Building Project
Initial phone call to discuss your needs
On-site meeting to review access and position
Proposal and payment schedule generated
Second meeting (with your architect, if applicable) to finalize plans
Step 2
Preparing for Your Innovative Learning Structures
Purchase order is released
Production schedule and supply timeline created
Inspections scheduled (customer handles inspection fees)
Materials ordered
Step 3
Off-Site Building Begins!
Exterior walls constructed (approximately 15 days)
Roof and interior wall constructed (approximately 10 days)
Site visit to ensure readiness
On-site construction schedule created
Subcontractors engaged and scheduled
Deliveries scheduled
Step 4
Erecting Your New Educational Structure
Excavation and rebar installation
Concrete footings and slab poured
Exterior walls secured with lock-in footing and slab
Doors, windows, and roof installed
Step 5
Readying Your Avendren Building for Occupancy
Interior walls installed, including electrical wiring, and vinyl coverings
Roof insulation and HVAC connections completed
T-bar, drop light fixtures, and fire sprinklers installed
Flooring installed
Step 6
Final Inspections and First Day of Class
Walkthrough with school representatives and Avendren team member
Final inspections signed off